Clean Room 2
| Project profile |
Complete mechanical and electrical fit out for a new 40 000 sq ft production facility |
| Project specification |
Class 100,000, clean rooms for primary and secondary use |
| Project duration |
12 weeks |
| Project value |
£380 000 |
Services installed
- Close control air conditioning
- Central plant ventilation
- Doors and partitions
- Power distribution and wiring
- Lighting
- Fire detection system
- Laminated ceilings
On completion, a programme of testing and validation was undertaken on all systems.
|