Computer Room Case Study 3

The computer room at the offices in Plymouth The computer room at the offices in Plymouth

Project profile “Turnkey” installation of environmental services for a computer room upgrade in Plymouth
Project Value £220,000

The 200 m2 facility was created to cater for expansion of the main computer room, and services installed include:

  • Close control air conditioning
  • Raised modular floor
  • Fire detection and suppression
  • High sensitivity smoke detection
  • Water leak detection
  • Doors and partitions
  • Computer power distribution panel and cabling

The project was completed within 6 weeks of order, during which period the existing facilities remained live.