Computer Room Case Study 3
| Project profile |
“Turnkey” installation of environmental services for a computer room upgrade in Plymouth |
| Project Value |
£220,000 |
The 200 m2 facility was created to cater for expansion of the main computer room, and services installed include:
- Close control air conditioning
- Raised modular floor
- Fire detection and suppression
- High sensitivity smoke detection
- Water leak detection
- Doors and partitions
- Computer power distribution panel and cabling
The project was completed within 6 weeks of order, during which period the existing facilities remained live.
|